Repair Methodology of Barwidgee Creek Bridge

Repair Methodology (Method, Materials) And Costs Estimations Of Barwidgee Creek Rail Trail Bridge

Project Scope

Level 2 inspection of Barwidgee Creek Rail Trail Bridge to assess 2012 flood damage and advise on repair methodology and specification for the required repair and maintenance.

The following tasks were delivered successfully:

  • Level 2 Detailed Visual Inspection
  • Analysis of Structural Integrity
  • Identification of Defects
  • Preparation of Repair Methodology and Cost Estimations Report

Project Ref. No. : TC20-P215

Client : Alpine Shire Council

Completion Date : 13–July–2021